Taxpayers slam Houston government over paving cost overruns

Author: Devin Drover 2026/10/26

The Canadian Taxpayers Federation is demanding the Houston government regain control of soaring paving costs, following a new auditor general report that found government projects routinely come in over budget.

“The auditor general just confirmed what taxpayers already know: The Houston government can’t build anything on budget,” said Devin Drover, CTF Atlantic Director. “With debt already out of control, Premier Tim Houston cannot keep letting paving costs spiral.”

The Houston government budgeted about $634 million for paving work over the last five years, but spent almost $850 million. That’s $215 million in over-budget spending or about $118,000 every single day for five years.

The report also found that the government is not making evidence-based decisions when selecting and prioritizing pavement projects, while many roads remain in poor condition.

“Provincial roads are in rough shape even after the Houston government blew through its paving budget,” said Drover. “Taxpayers are paying top dollar for bottom-of-the-barrel roads and the government can’t explain how it picks which roads get fixed.”

The paving overruns come as the Houston government sinks deeper into debt. The provincial government is projected to borrow more than $1.4 billion this year. Interest charges on the debt will cost taxpayers more than $1 billion this year or about $2.8 million every day.

“Houston is blowing his budgets on everything from paving to program spending and sending the bill to tomorrow’s taxpayers,” said Drover. “Nova Scotians can’t afford a government that treats its budget like a suggestion.

“Houston needs to rein in spending, stop borrowing money and show taxpayers they’re getting value for every dollar spent.”

 


A Note for our Readers:

Is Canada Off Track?

Canada has problems. You see them at gas station. You see them at the grocery store. You see them on your taxes.

Is anyone listening to you to find out where you think Canada’s off track and what you think we could do to make things better?

You can tell us what you think by filling out the survey

Franco Terrazzano
Federal Director

Hey, it’s Franco.

Did you know that you can get the inside scoop right from my notebook each week? I’ll share hilarious and infuriating stories the media usually misses with you every week so you can hold politicians accountable.

You can sign up for our Action Update emails

Looks good!
Please enter your first name
Looks good!
Please enter your last name
Looks good!
Please enter a valid email address
Looks good!
Please enter a valid postal code. Ex. K1K1K1

We take data security and privacy seriously. Your information will be kept safe.